4.1 (Optional) Concrete Platform Scenario

4.1.1 Determining the Pre-fab. Module Installation Position

Prerequisites
Concrete platform levelness is critical to pre-fab. module installation. Ensure that
the concrete platform meet requirements before installing pre-fab. modules.
Context
Before installing a pre-fab. module, determine its installation position and
direction based on site space.
Preparations
Tools: marker, ink foundation, long leather measuring tape
Materials: none
Skill requirement: skilled technician
Procedure
Step 1 Determine the reference points for installing a pre-fab. module on the concrete
platforms. Mark the reference points using a marker.
Issue 01 (2021-04-20)
4

Installing a Pre-fab. Module

The field meets site requirements.
Before installing a pre-fab. module, check the height of concrete platforms
and ensure that the height (altitude) error between the upper surfaces of all
platforms does not exceed 5 mm.
CA UTION
Copyright © Huawei Technologies Co., Ltd.
4 Installing a Pre-fab. Module
30

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents