Site Requirements; Site Selection Requirements; Field Requirements - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)

2.1 Site Selection Requirements

2.2 Field Requirements

The FusionDC1000 can be installed on bases or concrete platforms depending on
the actual scenario. The site requirements vary with the selected installation
mode.
Issue 01 (2021-04-20)
The power supply is stable and reliable.
The communication and traffic are convenient.
The site is far away from dust, smoke, harmful gas, and corrosive, flammable,
or explosive objects.
The site is not on a low-lying land, and above the highest water level of that
area.
The site is far away from sources of strong variation, loud noises, and strong
electromagnetic interference.
The ground is solid without spongy or soft soil, and is not prone to water
aggregation or subsidence.
The site is in an open area, meets the pre-fab. module installation and
maintenance requirements, and meets the heat dissipation requirement of the
smart cooling product outdoor units.
The site is at least 50 m away from residential areas.
The site is far away from a class D environment or 500 m away from the
seashore.
NO TE
For a specific project, select the product specifications based on the application
environment. For example, in a class B environment 3700 m away from the seashore,
the smart cooling product outdoor unit can be a common outdoor unit. In a class C
environment 500–3700 m away from the seashore, the smart cooling product outdoor
unit must be a class C outdoor unit.
Copyright © Huawei Technologies Co., Ltd.
2

Site Requirements

2 Site Requirements
15