Installing Cables Outside the Pre-fab.
9.1 Connecting Input Power Cables for the Pre-fab.
Module
Preparations
Tools: crimping tool, Phillips screwdriver, adjustable wrench, cable cutter, heat gun
Materials: cable tie, cable, terminal, heat shrink tubing
Skill requirement: skilled technician
Procedure
Step 1 Open the door of the power PDB.
Step 2 Remove the plugs from the two cable holes at the bottom of the power PDB.
Figure 9-1 Removing the plugs from the cable holes
Step 3 Remove the transparent cable protection panel from the power PDB busbar.
Issue 01 (2021-04-20)
Copyright © Huawei Technologies Co., Ltd.

9 Installing Cables Outside the Pre-fab. Module

Module
97

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents