Hoisting And Securing The Pre-Fab. Module - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)

4.2.3 Hoisting and Securing the Pre-fab. Module

Prerequisites
To facilitate subsequent installation, ensure that the pre-fab. module is level after
hoisting.
Context
Ensure that the crane and steel ropes can bear the load weight.
Table 4-3 Parameters for hoisting a pre-fab. module
Weight
Net weight: <
14,000 kg
Hoisting Precautions
Stage
Before hoisting
During hoisting
Issue 01 (2021-04-20)
NO TICE
Pre-fab. module bases have been installed and leveled.
Select an appropriate crane based on standards of the crane company, and
ask a professional to assess the crane onsite.
Twistlocks in pre-fab. module bases are in correct positions.
The hoisting ropes are available.
The doors of the pre-fab. module to be hoisted are closed.
The weather is good without wind when a pre-fab. module needs to be
hoisted outdoors.
Steel
Rope
Length
> 12.5 m
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
Ensure that the twistlocks in container bases are in correct
positions.
Ensure that the steel ropes are securely connected.
Do not allow any unauthorized people to enter the
hazardous areas and never stand under the crane arm
during hoisting.
Copyright © Huawei Technologies Co., Ltd.
Steel Rope
Dimensions (H x W x D)
Quantity
4 PCS
2896 mm x 2438 mm x 12192 mm
4 Installing a Pre-fab. Module
43