Installing Cables; Cable Routes - Huawei FusionModule500 User Manual

Smart mini data center
Hide thumbs Also See for FusionModule500:
Table of Contents

Advertisement

FusionModule500 Smart Mini Data Center
User Manual (ECC800e)
3.
Figure 2-71 Installing a CIM
----End

2.3 Installing Cables

2.3.1 Cable Routes

Principles of cable routes: The signal cable and power cable are routed along the right and left
of the cabinet rear door, respectively; When the cables are routed along the cabinet front door,
the power cable is on the right and signal cable on the left.
The following figure shows the cable routes from the top of four cabinets.
Issue 07 (2019-12-20)
Ensure that the attaching area is clean.
Ensure that the fastener is firmly attached with even strength.
Clamp the CIM to the fastener.
The 24 U cabinet does not involve cable routing from the top of the cabinet front door.