Figure 4-16 Removing a BIM
Step 3 Clamp the BIM whose network parameters are cleared to the fastener.
Step 4 Connect one end of the BIM cable to the pin port on the BIM.
Step 5 Press the networking switch on the BIM for 2 seconds based on the battery number
corresponding to the new BIM. When the RUN/ALM indicator turns from steady red to
blinking green at super short intervals, and finally to blinking green at long intervals, the BIM
connects to the CIM network.
Step 6 After checking that the BIM installation and networking are complete, on the home screen of
the CIM, choose Monitoring > CIM System > Running Control, click BIM start blinking,
and select the corresponding battery number from the range of 0–300. If the BIM blinks
successfully, the installation succeeds. If the BIM fails in blinking, check the cable
connections and reinstall the BIM.
Figure 4-17 Setting the BIM blinking
Step 7 Repeat
Issue 07 (2019-12-20)
If the BIM blinking function is successfully enabled, click BIM stop blinking and select the
corresponding battery number from the range of 0–300 to stop the BIM from blinking.
Step 3–Step 6
until all replacement BIMs are successfully installed and networked.
After all faulty BIMs are replaced, the ALM indicator on the CIM turns off.