kVA/10 kVA UPS)
Battery capacity
Max. current
Step 5 Switch on the QF3 circuit breaker (or any circuit breaker from QF4 to QF7) of the PDU5000.
Step 6 (Optional) Turn on the rPDU circuit breaker.
----End

3.2 Power-on Commissioning for the Monitoring System

3.2.1 Preparations and WebUI Login

Prerequisites
Table 3-2 User rights
User
Name
admin
operator
WebUI operating environment requirements:
Procedure
Step 1 Connect a network cable between the PC network port and the WAN port (protected by a
security mechanism) on the ECC800e.
Table 3-3
Table 3-3 Default IP addresses for the WAN and LAN ports on the ECC800e
Port
Issue 07 (2019-12-20)
Preset
Password
Changeme
Changeme
Operating system: Windows 7 and later versions
Browser: Internet Explorer 8.0 and later versions; Firefox 38.0.5 and later versions;
Chrome 46.0.2490.80 and later versions
lists the default IP addresses for the WAN and LAN ports on the ECC800e.
Copyright © Huawei Technologies Co., Ltd.
Default Value
3 kVA/6 kVA UPS:
40 Ah
10 kVA UPS: 65 Ah
2 A
Description
The admin user has all WebUI operation rights.
The operator user has no rights for parameter setting, control,
and maintenance that may affect system running.
Default IP Address
3 Commissioning Guide
Setting Value
Set as required
Battery capacity = Capacity of a
single battery string x Number of
parallel battery strings
Set as required