7.1 Installing External Input Power Cables
Prerequisites
Pre-fab. modules and external cable trays have been installed.
Preparations
Tools: crimping tool, Phillips screwdriver, adjustable wrench, cable cutter, heat gun
Materials: cable tie, cable, terminal, heat shrink tube
Skill requirement: skilled technician
Procedure
Step 1 Open the door of the main input PDB.
Step 2 Route the external input power cables into the pre-fab. module through the feeder window, as
shown in
Issue 02 (2020-01-15)