A.1 Battery Shallow Discharge Test
To facilitate operation and maintenance, a battery shallow discharge test can be configured in
the PLC function.
Prerequisites
Only the UPS2000-G-(6 kVA–10 kVA) and UPS2000-G-3 kVA (dual live wires) support a
battery shallow discharge test on the ECC800e.
You need to manually configure the battery shallow discharge test based on requirements.
The system type is FusionModule500.
1. It is recommended that you perform a battery shallow discharge test only in a class 1
2. After the UPS is powered off, the battery maintenance period of the UPS will be
3. During a battery shallow discharge test, if the mains outage occurs, the backup capacity
Procedure
Step 1 Log in to the ECC800e WebUI as an administrator.
Step 2 Choose System Settings > PLC.
Step 3 Set Enable PLC function to Yes and click Submit.
Step 4 Select 4 in the Logic List area and click Activate. Status then displays green.
Issue 07 (2019-12-20)
power grid scenario after confirming with the customer. If the power grid is not stable, do
not perform the battery shallow discharge test.
recalculated.
may be inconsistent with the rated capacity.
Copyright © Huawei Technologies Co., Ltd.

A FAQ

A
FAQ
200

Advertisement

Table of Contents
loading

Table of Contents