FusionModule500 Smart Mini Data Center
User Manual (ECC800e)
3.1 Power-On Commissioning for the Power Supply and
Distribution System
Prerequisites
You have completed the
Configure an upstream protective device that meets the overload and short-circuit protection
requirements for the Converged Cabinet.
Context
Figure 3-1
Issue 07 (2019-12-20)
2.4 Checking After
shows the circuit breakers on the PDU5000 front panel in the Converged Cabinet.
The PDU5000 shown in the following figure is for reference only.