Huawei FusionModule1000A Commissioning Manual

Huawei FusionModule1000A Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

Quick Links

FusionModule1000A40 Prefabricated All-in-One
Data Center
V200R003C10
Commissioning Guide
Issue
02
Date
2019-12-20
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei FusionModule1000A

  • Page 1 FusionModule1000A40 Prefabricated All-in-One Data Center V200R003C10 Commissioning Guide Issue Date 2019-12-20 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    About This Document About This Document Purpose This document describes how to power on and commission the FusionModule1000A prefabricated all-in-one data center (FusionModule1000 for short) in terms of safety precautions, preparations, power-on check, power on commissioning, joint commissioning, power-off, and core device commissioning. It provides you a quick grasp of how to commission the prefabricated all-in-one data center.
  • Page 4 Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues. Issue 02 (2019-12-20) Updated the safety information. Issue 01 (2019-07-15) This issue is the first official release. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    7.1.2 Commissioning the Logic Load Disconnection (Powering-Off) of the Power Supply System Under Normal Temperature ..................................33 7.2 Commissioning the Cooling System ........................... 34 7.3 The Management System Commissioning ......................... 34 Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 6 8.4.2.2.3 Setting the Transparent Transmission Function for the ECC800 Collector ............95 8.4.3 Scenarios for Connecting the server ........................96 8.4.3.1 Setting SMS ................................96 8.4.4 Scenarios for Connecting the LAN Switch ......................98 Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 7 8.5.2 Commissioning Fire Extinguishing Devices (CE) ....................112 8.5.2.1 Commissioning the Extinguishant Control Panel (CE) ..................112 8.5.2.2 Commissioning the Emergency Light (CE) ......................112 8.5.2.3 (Optional) Commissioning the VESDA ......................114 A Acronyms and Abbreviations ....................116 Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 8: Safety Information

    The "NOTICE", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
  • Page 9  Keep irrelevant people away from the equipment. Only operators are allowed to access the equipment.  Use insulated tools or tools with insulated handles, as shown in the following figure. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 10  To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 11: Personnel Requirements

    Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements  Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations.
  • Page 12 When selecting, connecting, and routing cables, follow local safety regulations and rules. The static electricity generated by human bodies may damage the electrostatic-sensitive components on boards, for example, the large-scale integrated (LSI) circuits. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 13: Installation Environment Requirements

     Ensure that the equipment room provides good heat insulation, and the walls and floor are dampproof.  Install a rat guard at the door of the equipment room. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 14: Mechanical Safety

    Before hoisting objects, ensure that hoisting tools are firmly secured onto a load-bearing object or wall.  Ensure that the angle formed by two hoisting cables is no more than 90 degrees, as shown in the following figure. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 15 Do not climb higher than the fourth rung of the ladder from the top.  Ensure that your body's center of gravity does not shift outside the legs of the ladder. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 16 Metal shavings from drilling may short-circuit boards inside the equipment.  Obtain the consent from the customer, subcontractor, and Huawei before drilling.  Wear goggles and protective gloves when drilling holes. ...
  • Page 17: Cooling System Safety

    1.7 Pre-fab. Module Safety  Ensure that the installation environment meets the following requirements: − The ground must be solid without spongy or soft soil, and is not prone to subsidence. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 18: Battery Safety

    If a battery is disposed of improperly, it may explode.  The site must be equipped with qualified fire extinguishing facilities, such as firefighting sands and powder fire extinguishers. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 19 Commissioning Guide 1 Safety Information To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ...
  • Page 20: Others

     Exercise caution when powering off the rPDU or PDU2000. Doing so may affect the power supply to equipment, which will interrupt services. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 21 UPS output voltage level or frequency. Doing so may affect the power supply to equipment.  Exercise caution when setting battery parameters. Incorrect settings will affect the power supply and battery lifespan. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Precautions For Power-On Commissioning

    Operations marked as optional in chapters, sections, or procedures can be performed depending on the actual situation.  Huawei assumes no liability for any loss caused by unauthorized changes to the initial configuration parameters. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 23: General Power-On Commissioning Process

    FusionModule1000A40 Prefabricated All-in-One Data Center Commissioning Guide 3 General power-on commissioning process General power-on commissioning process Figure 3-1 shows the general power-on commissioning process. Figure 3-1 General power-on commissioning process Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 24: Preparations For Power-On Commissioning

    Table 4-1 Tools Tools Phillips screwdriver Flat-head screwdriver Utility knife Multimeter Electroprobe Network cable tester Cable tie Insulation tape Marker ESD gloves Step ladder (2 m) ESD wrist strap Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 25 This table may not list some tools required at specific sites. Onsite installation personnel and technical support personnel should prepare tools based on site requirements.  Some dedicated tools and installation materials provided with the equipment may not be listed in this table. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 26: Reference Documentation

    Familiar with the cooling system configurations and the operations for each core device in the FusionModule1000 With cooling engineer qualifications Management With knowledge in the hardware and software of the prefabricated Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 27: Preparing For The Power Supply And Distribution System Power-On Commissioning

    Step 3 Understand the initial configurations of the power supply and distribution system by referring to the power supply and distribution device initial configuration table. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 28: Preparing For The Cooling System Power-On Commissioning

    Table 4-4 Water quality and pressure requirements Item Allowed Value Hydrogen ion pH: 7–8.5 Conductivity at 20ºC (σ 125–1250 μS/cm ≤ 100 mg/L Inlet water hardness specifications Water refill pressure 0.1–0.7 MPa Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 29: Preparing For The Management System Power-On Commissioning

    For the diagrams and tables, see the initial configuration parameter manual for the solution in use. Procedure Step 1 Understand the layout of monitoring devices by referring to the monitoring device layout diagram. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 30: Preparing For The Fire Extinguishing System Power-On Commissioning

    Step 1 Understand the layout of fire extinguishing devices by referring to the fire extinguishing device layout diagram. Step 2 Understand the running of the fire extinguishing system by referring to the fire extinguishing system conceptual diagram. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 31: Check Before Power-On

     Cables are placed properly and not tense at turning points.  Cable routes are straight and smooth, and do not intersect inside a cabinet. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 32 59–61 Hz   Battery Check the number of The batteries are batteries. correct in quantity and intact.  Check battery  connection. Batteries are connected based on  Measure the battery Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 33 Smart cooling Check the pipe The refrigerant product pipe connections for the circulation pipeline, connection air-cooled precision humidifier water refill pipeline, and condensate Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 34 Lighting system Component Check the lighting device  Devices are installed installation and installation and in positions shown in connection connection. the lighting device layout diagram.  Cables are correctly connected. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 35: Power-On Commissioning

    FusionModule1000 level by level. For equipment with dual power inputs, circuit breakers of both power inputs must be switched on. Step 3 Verify that the power-on process is normal. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 36 The magnetic lock indicator is system door green when the pre-fab. module door is closed.  The magnetic lock indicator is red when the pre-fab. module door is open.  The pre-fab. module door can Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 37 (CE) control panel  The power indicator is on.  The alarm indicator is off. Smoke detector Indicator The indicator blinks once every The indicator blinks once every Heat detector Indicator Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 38 Initial configurations must be verified before the first power-on after installation or restart after a long power-off period.  Equipment with initial configurations can be powered on only after the initial configurations are verified ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 39: System Commissioning

    Step 6 Check whether the power supply to the downstream devices is normal. During the operation, if the power supply to the downstream devices is normal, the switchover between the two power supplies is successful. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Commissioning The Logic Load Disconnection (Powering-Off) Of The Power Supply System Under Normal Temperature

    Step 4 Verify whether the systems run stably after power-on. The FusionModule1000 meets requirements if its devices are intact and systems are normal after powered off, and systems run stably after power-on. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 41: Commissioning The Cooling System

    Before putting the FusionModule1000 into use, you must commission the management system to ensure normal running. 7.3.1 Preparing for Commissioning the Management System Tool Preparations Multimeter, network cable tester, and RJ45 crimping tool Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 42: Commissioning The Management System

    Enter the initial user name and password on the ECC800 WebUI to log in to the ECC800 WebUI. Check the connections of all monitoring devices by referring to the monitoring device layout diagram. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 43: Commissioning The Fire Extinguishing System (Standard)

    Verify that all devices in the initial configuration table communicate with the management system properly. Check that the views and videos in the management system are consistent with the running status of the data center. If any inconsistency is found, contact Huawei technical support. ----End 7.4 Commissioning the Fire Extinguishing System...
  • Page 44 Step 3 Check whether the fire alarm control panel displays any alarm. If an alarm is displayed, clear the alarm before performing follow-up operations. Step 4 Press KEY ON/OFF, QUERY TIME, and MANUAl/AUTO in turn to set the fire alarm control panel to the automatic mode. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 45 After short-circuiting the 26 and GND terminals, remove the conducting wire if an alarm has been triggered. Figure 7-3 Short-circuiting terminals 26 and GND Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 46 The fire alarm control panel reports another fire alarm, the fire alarm horn/strobe is triggered, and the gas release countdown starts (the countdown period is configurable and set to 30s by default). Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 47 Disconnect the red and black cables from the pressure announciator, as shown by (1) in Figure 7-8. Short-circuit the cables from the fire alarm control panel to the pressure announciator, as shown by (2) in Figure 7-8. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 48 Figure 7-8 Short-circuiting the pressure announciator terminals (1) Red and black cables to the pressure (2) Cables to the fire alarm control announciator panel Step 9 Commission the emergency start/abort switch. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 49 Press RESET on the fire alarm control panel to reset the fire alarm control panel. Set the fire alarm control panel to the AUTO state. Hold the body of the smoke or heat detector, and turn the detector body to separate it from the base. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 50 Reinstall the heat detector in a similar way as reinstalling the smoke detector, as shown in Figure 7-13.  After the smoke detector or heat detector is reinstalled, the corresponding fault indicator turns off in about 3s. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 51 Step 11 Press RESET to reset the fire alarm control panel. Step 12 (Optional) Check whether the fire alarm signals are reported to the management system. Step 13 Reconnect cables to the electromagnetic valve. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 52 Remove screws securing a safety pin. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 53 FusionModule1000A40 Prefabricated All-in-One Data Center Commissioning Guide 7 System Commissioning Figure 7-15 Removing screws Loosen the remaining three screws. Figure 7-16 Positions of the screws Remove the safety pin. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 54: Fire Extinguishing System Commissioning (Ce)

    To avoid damage to the heat detector, keep a proper distance between the heating device and the heat detector during the commissioning. Preparations Tools: multimeter, smoke pistol, heating device, flat-head screwdriver, Phillips screwdriver, step ladder Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 55 Figure 7-18 Auto & Manual indicator position diagram Step 5 Check whether the extinguishant control panel displays any alarm. If an alarm is displayed, clear the alarm before performing follow-up operations. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 56 Step 7 Heat the heat detector using a heating device until the heat detector indicator changes from blinking once every six seconds to steady on to trigger a heat detector FIRE RELAY alarm. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 57 Step 8 Check whether the electrical actuator has been activated. Step 9 Commission the pneumatic switch. Pull up the reset button on the pneumatic switch to short-circuit the cables within to simulate an extinguishant release. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 58 Wait for one minute and turn the Enable Control key rightward. After the LCD changes from EEE to Ad, press Reseton the extinguishant control panel to reset the extinguishant control panel. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 59 Figure 7-26 Loop 1 FAULT RELAY indicator on Hold the smoke detector, and rotate it clockwise to install it to the base. Step 11 Simulate a cable disconnection fault for the heat detector. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 60 Step 13 Flip the Enable Control key rightwards, reset the extinguishant control panel by pressing Reset on it, and then flip the Enable Control key leftwards to reset the key. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 61: Commissioning Core Components

    02311FTC-001 Systems Context Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Switch on all SPD circuit breakers in the integrated UPS.
  • Page 62 . On the device configuration screen, you can set thresholds for parameters. The following table lists the system configuration attributes and values. Table 8-2 System configuration attributes and values Item Value Description Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 63: Commissioning The Integrated Ups

    Documents: integrated UPS user manual, power supply and distribution device layout diagram, power supply and distribution system diagram, power supply and distribution device initial configuration table Skill requirement: power distribution engineer Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 64 UPS.  During the UPS power-on commissioning, you are not allowed to modify the UPS initial configurations if not authorized by onsite Huawei engineers.  UPSs can work in single or parallel mode. Check that the initial configurations are consistent with the configurations in the initial configuration table for the solution in use.
  • Page 65 If a battery is 12 V, the number of cells is equal to the number of batteries multiplied by 6. If a battery is 2 V, the number of cells is equal to the number of batteries. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 66 When the UPS is started, perform a battery capacity test to ensure that battery parameters are correctly displayed. For details, see the integrated UPS user manual. Step 9 After verifying that the initial configurations are correct, switch on the integrated UPS output circuit breakers. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Commissioning The Mdu

    Yellow A major alarm has been generated for the integrated UPS, and the buzzer buzzes at an interval of 0.5s. Green A warning has been generated for the integrated UPS, or Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 68 Pin 4: positive receive end on the MDU  Pin 5: negative receive end on the MDU (5) USB Host  After installing the WiFi module, connect the WiFi module to the UPS using the Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 69: Commissioning Smart Cooling Products

    During the MDU power-on commissioning, you are not allowed to modify the MDU initial configurations unless you are authorized by onsite Huawei engineers. Step 3 Enter a user name and password to access the MDU, set the user name, password, time, and language, and check that the initial parameter settings are correct.
  • Page 70 Before power-on, clear dust, dirt, and foreign matter from the cabinet; otherwise, the water pump may be blocked, resulting in drainage failure or serious equipment malfunction. Step 3 Verify the initial configuration of the air cooled precision smart cooling product. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 71: Initial Dip Switch Configuration For T/H Sensors

    Huawei engineers. Step 4 Tap Indicates on the main screen, and tap Confirm on the dialog box that appears. If the start succeeds, the system prompts that the command is successfully executed.
  • Page 72: Teamwork Initial Configuration

    1 on the LCD is the master, which collects, processes, and delivers data. Figure 8-6 shows the teamwork topology for air-cooled precision smart cooling products. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 73 A non-green frame indicates the other device in the group, as shown in Ground Red indicates that a critical alarm is generated, color: red, bright gray as shown in Bright gray indicates that the device is operating without any Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 74 The number of the Set the assigned group No. teamwork controlled teamwork control group, which is the number. same for all the devices in the group. Smart Smart cooling product Set the assigned unit Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 75 If the networking mode is changed on the screen, the software will restart and then run in the new networking mode. Number of Number of the smart Total number of the Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 76 Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 77 T/H logically controlled by sensors. using the acquired value of the configured cold aisle T/H sensor. Hot aisle When this parameter is This parameter can be Disable Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 78 Check whether the number of online devices in the topology is the same as the actual number of devices. − If yes, the check is complete. − If no, check the cable connection and the teamwork settings. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 79: Initial Configuration Of Temperature And Humidity

    You need to obtain permission before changing system settings. Only trained and qualified personnel can change settings excluding the control type and set point of the T/H sensor. Figure 8-8 Setting temperature and humidity values Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 80 After the Temperature and humidity Set this parameter as setpoint control type and the humidity value required.40%–60% RH under this type are set, the device recommended conducts humidifying or dehumidifying based on the settings. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 81: Commissioning Monitoring Components

    ECC800. Table 8-9 Default IP addresses for the WAN and LAN ports on the ECC800 Port Default IP Address WAN_1 192.168.8.10 WAN_2 192.168.0.10 LAN_1 and LAN_2 192.168.248.10 Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 82 Click the Advanced tab and select Use TLS1.1 and Use TLS1.2. (Optional) Click the Connections tab and select LAN settings. (Optional) On Proxy server, clear Use a proxy server for your LAN. Click OK. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 83 Add the ECC800 IP address to the list of trusted sites. Figure 8-10 Adding an address Enable file download and set the security level of the trusted site to low. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 84 Enter to enter the WebUI login page. Figure 8-12 WebUI login page On the login page, enter the preset user name admin and preset password Changeme, set the language, and click Log In. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 85: Optional) Commissioning The Ibox And Ibat

    After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the default password in time or password loss after changing.
  • Page 86: Networking Iboxs And Ibats In Wireless Mode

    After the networking is complete, if the ALM indicator on the iBOX is steady on, the number of devices online is smaller than the value of iBAT Number. Check that iBAT Number is set to a correct value and that the iBAT is successfully networked. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 87: Commissioning Access Control Components

    Step 9 Remove the cover of the emergency door release button using a Phillips screwdriver, remove the glass, and rotate the door handle clockwise to open the pre-fab. module door. If the door can be opened, the emergency door release button is working properly. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Optional) Neteco Management

    8.4.1.2 Obtaining the NetEco Software License The NetEco software license is not provided together with software to the customer. Therefore, obtain the NetEco software license in advance. Obtain the license from the Huawei's enterprise support website.  For enterprise users: Log into Huawei's enterprise support website http://support.huawei.com/enterprise.
  • Page 89: Powering On A Server

    NetEco system server after logging in to the PowerEcho over the browser on a PC. Prerequisites  The browser version is Internet Explorer 11, Firefox 38ESR, Firefox 60ESR, Chrome 50 and Chrome 68. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 90: Installing The Ne Mediation

    After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 91: Neteco Menu Settings

    ----End 8.4.1.7 Logging In to the NetEco Client The NetEco uses the browser/server (B/S) working mode. You can log in to the NetEco using a web browser. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 92: Loading A Neteco License

    After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 93: Creating A Domain

    Container–ShapeNode, NetEco site: Holding down the Shift key and the left mouse button and then clicking on the corresponding lines can increase the small yellow dot. You can drag the small yellow dot to adjust the shape of the managed domain icon. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 94: Adding A Containerdc

    Step 4 Select ContainerDC from the Type drop-down list. Figure 8-14 Selecting the container Step 5 Select the ContainerDC to be added and drag the container icon to the Design area. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 95 If a container contains subdevices, you cannot delete the container. You can delete the container only after you delete subdevices in the container.  Delete one container. 1. Select Container and click Delete under Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 96 2. Add filter conditions, select multiple containers and click Delete. 3. In the displayed Confirm dialog box, click Yes.  Delete one module. Select Modular and click Delete under Figure 8-17 Deleting one module page Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 97: Process Of Adding A Device

    In the displayed Confirm dialog box, click OK. 8.4.1.11 Process of adding a device Prerequisites  You have logged in to the NetEco client by web browser.  You have the operation rights for Data Center Planning. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 98: Scenarios For Connecting The Ecc800 Collector

    Click Save. The device is added. 8.4.2 Scenarios for Connecting the ECC800 Collector 8.4.2.1 Commissioning Southbound Devices of ECC800 For details, see commissioning chapter in ECC800 Data Center Controller User Manual. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 99: Setting And Adding The Ecc800 Collector

    NetEco > network to ensure normal connection Communicati between the NetEco and the ECC800. Port number 31220 31220 Parameters Link to the WAN_1 WAN_1 monitoring IP address Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 100: Creating The Ecc800 Collector On The Neteco

    Devices subordinate to the ECC800 cannot be manually added or deleted. The devices can be deleted only if the ECC800 is deleted. The ECC800 whose system type is FusionModule1000A can be bound to an AIO Container. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 101  If NO is selected, change the authentication password for the ECC800 synchronized on the server. 3. Click OK. You are advised to change the password once every three months. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 102: Setting The Transparent Transmission Function For The Ecc800 Collector

    Select the device to be added and drag its icon to the management domain. Step 11 Click the device. In the device parameter area on the right, set device parameters according to the following table. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 103: Scenarios For Connecting The Server

    NetEco. This ensures that the NetEco can communicate with the SMS modem properly and the modem sends short messages to users properly. Prerequisites  You have logged in to the NetEco client by web browser Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 104 115200, 9600 or 4800. Mobile number for Phone number to which the short messages are sent. receiving NOTE notification Mobile number for receiving notification must be set according to the Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 105: Scenarios For Connecting The Lan Switch

    On the login page, enter the user name Admin and preset password Change_Me, and click Log In to enter the OMU Portal page. A message is displayed upon the first login Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 106 In the search results, click Edit in the row where Parameter Name is NTPIPC and set Value to 1. Click Save. After the camera NTP synchronization function is enabled, the camera, after being connected to the server, will automatically time-synchronize with the server. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 107 VCN IP address in the address box of the Internet browser, and log in to the OMU Portal system.  (Optional) Deploying IVS in Stack Mode. For details, log in to the https://e.huawei.com/, search for the VCN510&VCN520&VCN540 Product Documentation, open the documentation, and see the section Deploying IVS in Stack Mode. ...
  • Page 108: Setting Parameters On The Vcn Ivs Client

    After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 109 Step 4 Create a user. When connecting to the VCN on the NetEco, you need to log in to the VCN as a non-admin user. Log in to the VCN IVS as user Admin. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 110: Configuring Camera Parameters On The Neteco

    Management window is displayed. Step 2 In the navigation tree on the left, click Parameter Configuration. The Parameter Configuration page is displayed. Step 3 Specify parameters in the right pane based on Table 8-18. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 111: Registering With The Ocx Plug-In

    Step 5 Click Apply. ----End 8.4.4.1.4 Registering with the OCX Plug-in Only after you register with the OCX plug-in, you can play videos recorded by the camera on the NetEco in real time. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 112 Select Trusted sites and click Sites. Add the IP address of the client to the trusted site list, as shown in Figure 8-30. Figure 8-30 Trusted site list Click Add and then click Close. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 113 Restart Internet Explorer and enter the IP address to be accessed by the client. The page for watching videos is displayed. Click Install according to the prompt message. After the OCX plug-in is installed, you can watch the videos. If videos are not displayed, contact Huawei technical support.
  • Page 114: Adding A Camera Using Automatic Discovery

    After a camera is added, it will be displayed under the corresponding management domain on the Data Center Planning page. On the Data Center Planning page, you can set parameters such as the Name for the camera. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 115: Commissioning Fire Extinguishing Devices

    Step 1 Switch on the input power circuit breaker of the fire alarm control panel for the protected area by referring to the power supply and distribution system diagram. Step 2 Switch on the active and standby power supply to power on the fire alarm control panel. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 116 There are three buttons and one light emitting diode on the rear of the panel. The three buttons are S12, S11, and S10, respectively indicating switchover, adding one to the first two values, and add one for the last two values of the nixie tube. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 117 Step 6 Start or stop the fire alarm horn/strobe. When the keypad is unlocked, press HORN/STROBE to start or stop the fire alarm horn/strobe. After the alarm is started, the indicator beside the button turns on. ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 118: Commissioning The Emergency Lights (Standard)

    You can also turn off the emergency light by pressing and holding the TEST button for more than  If the result expected for each step appears, the emergency light is working properly. Figure 8-35 Small hole in the emergency light ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 119: Commissioning Fire Extinguishing Devices (Ce)

    The sockets of the emergency light have been powered on. Preparations Tools: step ladder, Phillips screwdriver Documents: power supply and distribution system diagram, fire extinguishing device layout diagram (CE) Skill requirement: fire engineer Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 120 The emergency light turns off, and the power indicator turns on. Step 6 Press the red button of the emergency light. The emergency light turns on. When you release the red button, the emergency light turns off. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 121: Optional) Commissioning The Vesda

    Step 3 Release smoke in the protected area using the smoke pistol. Verify that the VESDA alarm indicator lights up, and that an alarm is generated in the management system. Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 122 FusionModule1000A40 Prefabricated All-in-One Data Center Commissioning Guide 8 Commissioning Core Components After the operation is complete, press the reset button to reset the VESDA ----End Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 123: A Acronyms And Abbreviations

    Acronyms and Abbreviations automatic transfer switch Conformite Europende power distribution cabinet power distribution unit rPDU rack power distribution unit uninterruptible power system video cloud node VESDA very early smoke detection apparatus Issue 02 (2019-12-20) Copyright © Huawei Technologies Co., Ltd.