4.4 Preparing for the Power Supply and Distribution
System Power-On Commissioning
Prerequisites
The FusionModule1000 has been installed and has passed the insulation test.
Preparations
Tools: multimeter, Phillips screwdriver
Documents: power supply and distribution device layout diagram, power supply and
distribution system diagram, power supply and distribution device initial configuration table
Skill requirement: power distribution engineer
Procedure
Step 1 Understand the layout of the power supply and distribution devices by referring to the power
supply and distribution device layout diagram.
Step 2 Understand the control relationship of the power supply and distribution system by referring
to the power supply and distribution system diagram.
Step 3 Understand the initial configurations of the power supply and distribution system by referring
to the power supply and distribution device initial configuration table.
----End
Issue 04 (2020-01-17)
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Copyright © Huawei Technologies Co., Ltd.
4 Preparations for Power-On Commissioning
Personnel Skill Requirement
With knowledge in the hardware and software of the
prefabricated data center, familiar with basic
communications protocols, familiar with equipment
interfaces in weak-current systems, and proficient in
operating the NetEco management system
With weak-current engineer qualifications
Familiar with the fire extinguishing system
configurations and the operations for each core device
in the FusionModule1000
With fire protection engineer qualifications
Familiar with the overall configurations and layout of
the FusionModule1000
Experienced in data center maintenance
19