5.11.2 Confirming a NodeB Commissioning Task

This section describes how to confirm a NodeB commissioning task. After a NodeB passes the
service verification, the status of the NodeB commissioning task changes to Waiting for
Acknowledgement. You need to manually confirm that the commissioning is complete.
Context
If some alarms are still not cleared during the commissioning, it is recommended that you not
confirm the commissioning task. After you confirm the commissioning task, any alarm generated
during the commissioning cannot be viewed on the basis of a single NodeB on the Monitor tab
page. If any uncleared alarm exists during the commissioning, the alarm is reported again in the
Normal status.
Procedure
Step 1 Choose Configuration > Auto Deployment > NodeB Auto Deployment. The NodeB Auto
Deployment window is displayed.
Step 2 In the commissioning task list, select the commissioning task to be confirmed.
Step 3 Click
After the commissioning is complete, the M2000 performs the following operations:
l
l
----End

5.11.3 Confirming an eNodeB Commissioning Task

After the eNodeB health check is complete, the status of the commissioning task changes to
Awaiting_ack. In this case, you need to acknowledge the eNodeB commissioning.
Procedure
Step 1 On the M2000 client, choose Configuration > Auto Deployment > eNodeB Auto
Deployment. The eNodeB Auto Deployment tab page is displayed.
Step 2 Right-click the target commissioning task and choose Acknowledge from the shortcut menu.
The commissioning task is acknowledged.
----End

5.12 Reference to the GBTS Commissioning Interface

This section describes the interfaces and parameters for GBTS commissioning and facilitates
you to perform relevant operations for GBTS commissioning.
5.12.1 Interface Description: GBTS Commissioning
Issue 02 (2010-07-30)
Stop subscribing to the performance counters of the GBTS for service verification.
on the toolbar to confirm that the commissioning is complete.
Stop monitoring the alarms on the NodeB and its RNC.
Stop subscribing to the service verification performance counters of the NodeB.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Commissioning the MBTS in GL or UL Mode on the
M2000
5-43

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents