l
If every performance counter related to the CS and PS services is once displayed as a value that
is not 0, the M2000 considers the service verification a success, and the commissioning task
automatically switches to Confirming completed. Otherwise, the service verification persists.
Procedure
Step 1 Choose Configuration > Auto Deployment > GBTS Auto Deployment to open the GBTS
Auto Deployment window.
Step 2 On the GBTS List tab page, select one or multiple commissioning tasks, and then click
Alternatively, right-click the tasks, and then choose Open Service Verification Window from
the shortcut menu.
For details about the service verification window, see
Commissioning.
Step 3 View the service verification results and perform corresponding operations.
The accumulation values of the counters, which are collected in the time range between the start
of the service verification and the restart of the commissioning or the confirmation of the
commissioning completion, are displayed in the service verification window.
l
l
----End

5.5.4 Restarting a GBTS Commissioning Task

This section describes how restart a GBTS commissioning task that is still in progress according
to the actual requirement. A GBTS commissioning task in progress indicates that it is not in
Waiting or Completed status. If you restart a commissioning task, all commissioning operations
that are already performed are cleared, and the commissioning restarts from the OML detection.
Prerequisite
A GBTS commissioning task is created.
Procedure
Step 1 Choose Configuration > Auto Deployment > GBTS Auto Deployment to open the GBTS
Auto Deployment window.
Issue 02 (2010-07-30)
PS services: Uplink GPRS Verification and Downlink GPRS Verification
NOTE
The performance data collected for service verification is saved on theM2000 for 14 days. After 14 days,
the M2000 automatically deletes the data to release system resources.
If
is displayed in each counter value, you can infer that the GBTS service verification
succeeds. In this case, you can check and confirm the completion of the commissioning. For
details, see
5.11.1 Confirming a GBTS Commissioning
If
is displayed in the value of a certain counter, you can infer that the services related to
this counter are running abnormally. In this case, you need to rectify the fault. If the system
output indicates that the PS services are abnormal but no PS services exist actually, you can
confirm the completion of the commissioning.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Commissioning the MBTS in GL or UL Mode on the
5.12.1 Interface Description: GBTS
Task.
M2000
.
5-27

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents