5 Commissioning the MBTS in GL or UL Mode on the
M2000

Figure 5-2 eNodeB Auto Deployment tab page

Step 2 Upload the software and files required for eNodeB commissioning on the M2000.
1.
2.
3.
4.
5.
6.
7.
8.
9.
Step 3 Import the EDS file.
1.
5-10
Click
on the eNodeB Auto Deployment tab page. The Prepare File&Data dialog box
is displayed.
In the NE Software Version area, click Add. The Add dialog box is displayed. Specify
the related parameters in the displayed dialog box, such as NE type, version type, and local
file path.
In the RET Software area, click
the local PC.
In the RET Data area, click
uploaded in the local PC.
In the RET Template area, click
be uploaded in the local PC.
In the Test License area, click
uploaded in the local PC.
In the Prepare File&Data dialog box, click OK to return to the eNodeB Auto
Deployment tab page.
View the file uploading progress on the Prepare File&Data tab page below the eNodeB
Auto Deployment tab page.
Click
in the eNodeB Auto Deployment tab page. The Open dialog box is displayed.
Select the OM IP data template to be uploaded in the local PC.
Click
on the upper left of the eNodeB Auto Deployment tab page. The Import dialog
box is displayed, as shown in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
and select one or more RET files to be uploaded in
and select one or more RET data configuration files to be
and select the RET commissioning data template to
and select the eNodeB commissioning license to be
Figure