5.11 Confirming the Commissioning Task

After the M2000 finishes commissioning a base station automatically, the commissioning task
enters the to-be-confirmed state, waiting for manual confirmation that the commissioning is
complete.

5.11.1 Confirming a GBTS Commissioning Task

This section describes how to confirm the completion of GBTS commissioning. After the GBTS
service verification is complete, the commissioning task switches to Confirming completed
status, and you need to manually confirm the completion.
5.11.2 Confirming a NodeB Commissioning Task
This section describes how to confirm a NodeB commissioning task. After a NodeB passes the
service verification, the status of the NodeB commissioning task changes to Waiting for
Acknowledgement. You need to manually confirm that the commissioning is complete.
5.11.3 Confirming an eNodeB Commissioning Task
After the eNodeB health check is complete, the status of the commissioning task changes to
Awaiting_ack. In this case, you need to acknowledge the eNodeB commissioning.
5.11.1 Confirming a GBTS Commissioning Task
This section describes how to confirm the completion of GBTS commissioning. After the GBTS
service verification is complete, the commissioning task switches to Confirming completed
status, and you need to manually confirm the completion.
Context
If some alarms are still not cleared during the commissioning, it is recommended that you not
confirm the completion of the commissioning task so that you can view and handle these alarms
easily. After you confirm the completion, all GBTS alarms, which are generated during the
commissioning, cannot be viewed on the monitoring tab page on the basis of a single GBTS.
The alarms that are not cleared during the commissioning are reported again as common alarms.
Procedure
Step 1 Choose Configuration > Auto Deployment > GBTS Auto Deployment to open the GBTS
Auto Deployment window.
Step 2 In the commissioning task list, select the commissioning task to be confirmed.
Step 3 Click
After the commissioning is complete, the M2000 performs the following operations:
l
5-42
Expectation
Connection success rate > 95%. The calls are uninterrupted and none
of the calls get dropped till they are released. The voice is clear with
no loud noise.
on the toolbar to confirm the completion of the commissioning task.
Stop monitoring the alarms of the GBTS and the GBSC managing the GBTS.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3900 Series Multi-Mode Base Station
Commissioning Guide
Issue 02 (2010-07-30)

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents