Huawei OceanStor N8500 T Series Installation Manual page 53

Clustered nas storage system
Table of Contents

Advertisement

OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
Context
Stacking storage devices will damage devices; therefore, storage devices must be placed on
adjustable guide rails.
l
l
l
l
Procedure
Step 1 Install the left adjustable guide rail (with an L identifier).
1.
2.
Issue 02 (2015-09-22)
NOTICE
Each SUC is equipped with a pair of adjustable guide rails.
Guide rails can be flexibly adjusted from 600 mm to 900 mm, and installed in the cabinet
with a depth from 800 mm to 1200 mm.
Adjustable guide rails come preinstalled with square-hole positioning pins. If required,
change square-hole positioning pins to round-hole ones before installing adjustable guide
rails.
NOTE
You can find round-hole positioning pins in the accessory bag delivered with storage devices.
Three M6 screws are used to secure adjustable guide rails.
hole locations.
Figure 5-5 Screw hole locations
NOTE
If there is no scale marked on the channels, mark the scale from the bottom 1 U position upwards. Be sure
to horizontally line up the front and rear of the adjustable guide rail.
Align the underside of the adjustable guide rail with the desired U position on the front and
rear channels.
Extend the adjustable guide rail until the front and rear positioning pins protrude through
the holes on the front and rear channels.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 N8500 Installation (with the S2600T Storage System as the
Storage Unit)
Figure 5-5
shows the screw
44