SV2 Series Safety Shut-off Valves
The procedure outlined in the SV2 Series Valves Installation Instructions is designed to locate and quantify a gas
leak.
5. PROGRAMMING AND SETUP OVERVIEW
A. Connect Wiring
Connect the Modbus wiring per the HMI Tool or PC Tool installation instructions (whichever is used).
B. - C. Power Valve and Programming Tool and Complete Setup
Power the valve and the HMI Tool or PC Tool. The welcome screen should appear.
Follow the embedded wizards in the HMI or PC Tool to complete the setup of all applicable intelligent items as required. You may
reference the HMI/ PC Tool User manual, 32-00031.
6. FINAL WIRING AND STATIC CHECKOUT OVERVIEW
A. Test
CAUTION
• Cycle the valve several times with the manual fuel shut-off valve closed. Verify that the valve, accessory modules
and control system function properly
• Test each limit and interlock to ensure system operates correctly as defined in the applicable flame safeguard
control manual instructions.
• Follow burner management system checkout guidelines. For 7800 SERIES, refer to the "Checkout and Test"
document 65-0229.
• Perform any other recommended manufacturer or other required tests.
Troubleshooting
WARNING!