5.3.12 Setting and Adding a PMAC625 AC Meter

Prerequisites
The model of the three-phase AC power meter for the PDC is PMAC625.
In this example, a straight-through cable is used to connect the PMAC625 AC meter to the
COM port on the ETH converter.
When connecting devices, you are advised to add devices one by one and ensure that the view
is consistent with the real object. If all devices have been added and powered on, only the
BLINK function of the ETH converter can be used to identify the mapping between the
PMAC625 and ETH converter.
Procedure
Step 1 Set the PMAC625 communications address.
1.
2.
3.
Issue 06 (2020-01-02)
If the PDU2000-M(C) does not connect to the ECC800 properly, check whether the
cable between the PDU2000-M(C) and the ECC800 is connected properly, whether
the PDU2000-M(C) and ECC800 are running properly, and whether the input
parameters are consistent with the PDU2000-M(C) parameters.
Press
on the displayed screen after the PMAC625 is started. Press
entering the programming mode. Modify the password (1 by default) in blinking ones
digit by pressing
Figure 5-7 Programming screen of the PMAC625
Enter the communications address setting screen by pressing
to confirm the setting.
Select the place of the communications address value to be modified by pressing
or
, modify the communications address value (ranging from 1 to 247) by pressing
or
, and then press
Copyright © Huawei Technologies Co., Ltd.
or
, and press
to save the setting.