2) Install one power cable (hybrid cable, AWG10, 2C) connected to the baseband rack's
DC SPD terminal to the RRH-P4 power terminal. (Refer to the 'Caution for installing
the power cable').
3) Cut cable installed to the power terminal. Unsheathe outer cable sheath at 1.38 in.
(35 mm) length and peel off the inner wire at 0.39 in. (10 mm) length.
4) Insert a heat shrink tube (0.59 in./15 mm) for each inner wire and compress the wire
with pressure terminal (AWG10).
pressure terminal: AWG10, ring type, hole diameter: 0.2 in. (5.3 mm)
5) Align the heat shrink tube (-48 V: blue, RTN: red) at the compressed part of the
pressure terminal and shrink the tube using the heating gun.
6) Fix heat shrink tube (jelly type, 12/4, 1.97 in. (50 mm)] at stripped external sheath and
shrink the heat shrink tube using a heat gun. At this time, match the end of unsheathed
external cable and the end of heat shrink tube.