Figure 6-316 Hole positions on the channel steel (optional)
(1) Hole positions on the channel steel (The figure uses the C-shaped channel steel with the
opening facing downwards and one cabinet as an example. The figure shows the hole positions
on the channel steel when the cabinet is not installed against a wall. The channel steel model,
installation mode, whether holes need to be drilled on its sides, hole size, and the actual
number of cabinets are determined based on site survey data.)
Figure 6-317 Recommended channel steel dimensions (unit: mm)

6.6.2.2 Installing Rectifiers in the Inductor Cabinet

Context
Rectifiers are delivered separately, and baffle plates are placed in the fitting bag of
the inductor cabinet.
Procedure
Step 1 Install the rectifiers and baffle plates.
1.
2.
3.
4.
5.
6.
Issue 05 (2021-10-13)
Push the locking latch leftwards.
Pull out the handle.
Insert the rectifier into the slot and push it along the guide rails until it is in
position.
Push the handle in place and lock it.
Push the locking latch rightwards to secure the handle.
Install baffle plates for the vacant slots.