Figure 6-201 Installing parallel copper bars
----End
Installation on Channel Steel
● Huawei does not provide channel steel or expansion bolts used for securing
● Ensure that the surface of channel steel is level.
● The procedure for installation on channel steel is similar to that for installation
Issue 05 (2021-10-13)
NO TICE
channel steel. It is recommended that the customer purchase at least 50 mm
wide channel steel.
on the floor except the following steps:
Determine the mounting holes for the cabinets based on the marking-off
template (for installation on channel steel).
Drill mounting holes on the channel steel using a hammer drill.
If the nuts cannot be placed on the side of the channel steel, drill holes
near the mounting holes on the side of the channel steel to place the nuts
for securing the cabinet.
You are advised to use an electric pallet truck to move the cabinet to the
mounting holes in the channel steel.
Use M12x60 bolts to secure the cabinets on the channel steel.