UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-277 Drilling holes and installing expansion sleeves
(1) M12 bolt
(4) Expansion sleeve
Step 3 Remove the screws preinstalled on the copper bars in power cabinet 2 and store
them for future use.
Figure 6-278 Removing the preinstalled screws
Step 4 Move the cabinets to the mounting holes.
Step 5 Remove the power distribution covers from power cabinets 1 and 2.
Issue 05 (2021-10-13)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
(2) Spring washer
(5) Expansion nut
6 Installation
(3) Flat washer
(6) Concrete floor
244