Installation In Top Cabling Configuration; Installing Cabinets - Huawei UPS5000-H User Manual

100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Figure 6-112 Connecting a signal cable between the UPS and the SmartLi (only
for SmartLi 2.0)
(1) Monitoring interface unit in the master SmartLi cabinet
----End

6.4.2 Installation in Top Cabling Configuration

Cables can be routed from the top if the optional top cabling component is
configured.

6.4.2.1 Installing Cabinets

Installation on the Floor
Ensure that the installation floor is flat.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Issue 05 (2021-10-13)
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.
6 Installation
152

Advertisement

Table of Contents
loading

Table of Contents