UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Lifting trolley
Table 6-1
tools required, see the document for each component. Prepare tools based on site requirements.
6.1.3 Preparing Power Cables
● The UPS can generate large leakage currents. A circuit breaker equipped with a
● If the top cabling component and bottom cabling cabinet are not configured,
If the top cabling component and bottom cabling cabinet are not configured,
prepare wiring copper bars for mains input, bypass input, and output based on the
following drawings and current requirements.
Issue 05 (2021-10-13)
NO TE
lists only the common tools for installation and cable connection. For more dedicated
NO TICE
residual current device (RCD) is not recommended.
copper bars need to be prepared for the mains input, bypass input, and output,
which cannot be directly connected using cables.
Copyright © Huawei Technologies Co., Ltd.
Tools and Instruments
6 Installation
94