Huawei UPS5000-H User Manual page 131

100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Figure 6-57 Drilling holes and installing expansion sleeves
(1) M12 bolt
(4) Expansion sleeve
Step 3 Remove the UPS cabinet side panels.
Step 4 Remove the front panel from the bottom cabling cabinet.
Step 5 Move the cabinets to the installation positions.
Step 6 Combine the bottom cabling cabinet with other cabinets in the sequence of
bottom, top, and middle, and remove the connecting kits on the top of the left
and right sides.
Figure 6-58 Combining the bottom cabling cabinet
Step 7 Secure the cabinets.
Issue 05 (2021-10-13)
(2) Spring washer
(5) Expansion nut
Copyright © Huawei Technologies Co., Ltd.
6 Installation
(3) Flat washer
(6) Concrete floor
121