UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6.4 Single UPS Installation (1200 kVA, Three-Phase
Three-Wire)
During installation and cable connection, do not step on the front door baffle
plate and the door support at the bottom of the cabinet to prevent paint flake-off
and deformation. Otherwise, the front door will not be properly closed. Do not
step on the top of the cabinet to prevent deformation or collapse.
6.4.1 Installation in Standard Configuration
6.4.1.1 Installing Cabinets
Installation on the Floor
Ensure that the installation floor is flat.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Figure 6-92 Hole dimensions (unit: mm)
Step 2 Use a hammer drill to drill holes for installing expansion bolts and then install
expansion sleeves in the holes.
1.
Issue 05 (2021-10-13)
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Drill a hole into the concrete floor using a hammer drill. The hole depth
ranges from 52 mm to 60 mm.
Copyright © Huawei Technologies Co., Ltd.
6 Installation
140