Single Ups Installation (1600 Kva, Three-Phase Four-Wire); Installation In Standard Configuration; Installing Cabinets - Huawei UPS5000-H User Manual

100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6.5 Single UPS Installation (1600 kVA, Three-Phase
Four-Wire)
During installation and cable connection, do not step on the front door baffle
plate and the door support at the bottom of the cabinet to prevent paint flake-off
and deformation. Otherwise, the front door will not be properly closed. Do not
step on the top of the cabinet to prevent deformation or collapse.

6.5.1 Installation in Standard Configuration

6.5.1.1 Installing Cabinets

Context
Power cabinet 1 is transported separately, and power cabinet 2 and the bypass
cabinet are transported together.
Installation on the Floor
Ensure that the installation floor is flat.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Issue 05 (2021-10-13)
Figure 6-191 Installing mounting plates
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.
6 Installation
198