NetCol8000-E220 Modular Indirect Evaporative
Cooling System
User Manual
Figure 3-11 Tightening twistlocks
----End
Follow-up Procedure
After NetCol8000-Es are hoisted and installed, verify the installation to ensure
normal use of products and smooth subsequent installation.
Table 3-10 Installation checklist
No.
1
2
3
3.5 Unpacking
Issue 06 (2020-08-19)
Check Item
Contact between
NetCol8000-Es and
concrete platforms
Contact between
equipment and the
base
Equipment doors
Copyright © Huawei Technologies Co., Ltd.
Check Method
Partially tighten them
using a wrench.
Observe.
Open and close each
NetCol8000-E door
once.
3 Installation Guide
Criteria
Bolts and nuts are
tightened.
The equipment is in close
contact with and evenly
supported by the base.
All NetCol8000-E doors
can be smoothly opened
and closed.
40