Huawei NetCol8000-E220 User Manual page 42

Modular indirect evaporative cooling system
Hide thumbs Also See for NetCol8000-E220:
Table of Contents

Advertisement

NetCol8000-E220 Modular Indirect Evaporative
Cooling System
User Manual
Context
Table 3-5 Hoisting Precautions
Stage
Before hoisting
During hoisting
Table 3-6 Parameters for hoisting NetCol8000-Es
Weight
Net weight:
5700 kg
Tools: crane, marker, ink fountain, long leather measuring tape, socket wrench,
torque wrench, Phillips screwdriver, jack, steel hoisting rope, level, level gauge,
hammer drill, angle rule, claw hammer, vacuum cleaner
Materials: NetCol8000-E, expansion bolt, angle steel bracket
Procedure
Step 1 Prepare a concrete platform by referring to the following figures.
Issue 06 (2020-08-19)
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
The doors of NetCol8000-Es to be hoisted are closed.
Ensure that the steel ropes are securely connected.
Ensure that the weather condition is good without wind
when NetCol8000-Es need to be hoisted outdoors.
Do not allow any unauthorized people to enter the
hazardous areas and never stand under the crane arm
during hoisting.
Ensure that the crane is properly located and avoid long-
distance hoisting.
Keep the device stable and horizontal during hoisting, and
ensure that the diagonal gradient of the NetCol8000-E is
within 5 degrees.
Lift and land a NetCol8000-E slowly to prevent shock to
equipment inside it.
Remove the steel ropes after ensuring that the device is
placed evenly on the concrete platforms.
Steel Rope
Length
> 6.5 m
Copyright © Huawei Technologies Co., Ltd.
Steel Rope
Dimensions (H x W x D)
Quantity
4 PCS
6058 mm x 2438 mm x 3600
mm
3 Installation Guide
33