5.7 Commissioning Sensors

5.7.1 Commissioning a Multi-functional Sensor

If a multi-functional sensor is installed, perform the following steps to configure it.
Procedure
Step 1 Set multi-functional sensor parameters.
On the WebUI, choose Monitoring > Aisle > Multi-Func Sensor Group > Multi-Func
Sensor1 > Running Parameters, ensure that Smoke enable and Temp enable are set to
Enable, set High temperature alarm threshold and other parameters as required, and then
click Submit.
Step 2 Check the functions of the multi-functional sensor.
Table 5-24 Function commissioning
Check Method
Temperature and humidity
detection: View the running
information about the
multi-functional sensor on the
WebUI.
Issue 02 (2019-02-28)
If multiple multi-functional sensors are connected, commission one multi-functional sensor first and
then commission the other multi-functional sensors in the same way.
Copyright © Huawei Technologies Co., Ltd.
Normal Connection Status
You can view the current ambient temperature and
humidity.
5 Power-On Commissioning
125