ECC800 Data Center Controller
User Manual
Step 2 Add a UPS5000-E.
1.
2.
Table 5-4 Adding a UPS5000-E
Path
System
Settings >
Device
Management
3.
4.
----End
Issue 02 (2019-02-28)
Figure 5-2 UPS5000-E communication settings
Log in to the ECC800 WebUI as an administrator.
Add a UPS5000-E.
Parameter
Name
Device type
Connect to
Communications
port
Device address
Click Connect Test to check whether the UPS5000-E connects to the ECC800 properly.
If the UPS5000-E connects to the ECC800 properly, click Add Device.
If the UPS5000-E does not connect to the ECC800 properly, check whether the
cable between the UPS5000-E and the ECC800 is connected properly, whether the
UPS5000-E and ECC800 are running properly, and whether the input parameters
are consistent with the UPS5000-E parameters.
Choose Monitoring > System > ETH Converter Group > ETH Converter n >
Running Parameters and set Device name to ETH Converter_device position.
Copyright © Huawei Technologies Co., Ltd.
Setting
Select UPS5000 from the drop-down list box.
Select ETH Converter n from the drop-down list
box.
Select COM1/COM2 from the drop-down list box.
In this example, Device address is set to 1. During
actual configuration, set the device address for the
UPS5000-E based on the actual situation.
5 Power-On Commissioning