Install the Shelf and Backplane Cable
Figure 1-25 Installing the Rear Cover with Spacers
Continue with the
Step 6
Stop. You have completed this procedure.
NTP-A12 Install Ferrites
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Step 1
To attach ferrites to power cabling, complete the
page
To attach ferrites to wire-wrap pin fields, complete the
Step 2
Fields" task on page
Continue with the
Step 3
Stop. You have completed this procedure.
March 2003
"NTP-A12 Install Ferrites" procedure on page
This procedure describes how to attach ferrites.
Oval and/or block ferrites
NTP-A6 Install the Power and Ground, page 1-23
NTP-A8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections,
page 1-34
As needed
Onsite
None
1-58.
1-59.
"NTP-A13 Perform the Shelf Installation Acceptance Test" procedure on page
1-57.
"DLP-A30 Install Ferrites to Power Cabling" task on
"DLP-A31 Attach Ferrites to Wire-Wrap Pin
Cisco ONS 15454 Procedure Guide, R4.0
NTP-A12 Install Ferrites
1-60.
1-57