NTP-A9 Install the Electrical Card Cables on the Backplane
DLP-A25 Install Coaxial Cable With BNC Connectors
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Place the BNC cable connector over the desired connection point on the backplane.
Step 1
Figure 1-21 on page 1-50
cable connector.
Figure 1-21 Using a Right-Angle Connector to Install Coaxial Cable with BNC Connectors
Step 2
Position the cable connector so that the slot in the connector is over the corresponding notch at the
backplane connection point.
Gently push the connector down until the notch backplane connector slides into the slot on the cable
Step 3
connector.
Turn the cable connector clockwise to lock it into place.
Step 4
Tie wrap or lace the cables to the EIA according to Telcordia standards (GR-1275-CORE) or local site
Step 5
practice.
Route the cables to the nearest side of the shelf assembly through the side cutouts according to local site
Step 6
practice. The rubber-coated edges of the side cutouts prevent the cables from chafing.
Cisco ONS 15454 Procedure Guide, R4.0
1-50
This task installs the coaxial cable with BNC connectors.
None
DLP-A12 Install a BNC or High-Density BNC EIA, page 1-17
Required if you are using DS3-12, DS3XM-6, or EC-1 cards and are using
a non-high-density BNC interface