Figure 9-6 Wiring diagram
Step 4 Install thermal insulation foam on pipes.
----End

9.3 Installing Monitoring Devices

This manual does not cover the installation of upstream monitoring devices. For
the detailed installation methods, see
(NetEco Version) .
If the NetEco is deployed inside the pre-fab. module, it occupies space for server
cabinets. It is recommended that the NetEco be deployed under the ECC800 in the
A1 cabinet. The server, LAN switch, and IVS respectively occupy 2 U, 1 U, and 2 U
space.

9.3.1 (Optional) Installing ECC800 Accessories

Prerequisites
Required ECC800 accessories have been obtained.
Preparations
Tool: Phillips screwdriver
Materials: Micro SD card, SIM card, 4G antenna, RF_Z antenna
Issue 07 (2022-12-15)
NO TE
Wrap the electric heating belt before wrapping the thermal insulation foam, and the
thermal insulation foam covers the electric heating belt. Verify that the thermal insulation
foam can withstand a temperature greater than or equal to 200°C.
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Installing Devices Inside Pre-fab. Modules
iManager NetEco Product Document -
80

Advertisement

Table of Contents
loading

Table of Contents