Installation Guide
● Lines should be perpendicular or parallel, with an angle of 90 degrees at cross
points.
● The point where the reference lines intersect is the middle point for installing a
pre-fab. module base.
Step 3 Place bases based on the reference lines.
● Longitudinal and latitudinal symmetric lines are stamped on bases in the
factory. When installing bases, verify that the 400 mm edges of the bases are
parallel with the length direction of pre-fab. modules, and that the symmetrical
lines are aligned with the reference lines.
● After placing all the bases, measure the diagonal distances between the four
outermost bases for a pre-fab. module, and ensure that the diagonal length
deviation is within 5 mm.
Step 4 Mark the hole positions for installing pre-fab. module bases on the concrete
platforms using a marker.
Figure 5-7 Determining hole positions for installing a pre-fab. module base
● When marking hole positions for a base, ensure that the symmetric lines on the
base are aligned with the reference lines you marked.
● There are eight mounting holes for one single-capacity base. Mark all the hole
positions.
Step 5 Move away the pre-fab. module bases, and install expansion bolts in the base
mounting holes.
Issue 07 (2022-12-15)
NO TICE
NO TICE
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Installing Pre-fab. Modules
47

Advertisement

Table of Contents
loading

Table of Contents