Optional) Mounting Base Scenario - Huawei FusionModule1000A40 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
----End
Follow-up Procedure
After pre-fab. modules are hoisted and installed, verify the installation to ensure
normal use of products and smooth subsequent installation.
Table 5-2 Installation checklist
No.
1
2
3

5.2 (Optional) Mounting Base Scenario

Issue 07 (2022-12-15)
Figure 5-5 Securing an angle steel bracket
Check Item
Contact between pre-
fab. modules and
concrete platforms
Bolts and nuts
Pre-fab. module doors
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Installing Pre-fab. Modules
Check Method
Observe.
Partially tighten them
using a wrench.
Open and close each
pre-fab. module door
once.
Criteria
A pre-fab. module is
in close contact with
and evenly supported
by the concrete
platforms.
Bolts and nuts are
tightened.
All pre-fab. module
doors can be
smoothly opened and
closed.
45