Huawei FusionModule1000A40 Installation Manual page 122

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
Figure A-5 DPJ end connector
(1) Body
(3) Guarding
(5) Plastic-coated metal hose
Preparations
Tools: small cutter, scissors, wrench dedicated for feeder windows, glue gun
Material: sealant
Documents: none
Skill requirement: skilled technician
Procedure
Step 1 Cut the plastic-coated metal hose to facilitate connection between the metal hose
and the ferrule.
1.
2.
Step 2 Remove the sealant from the DPJ end connector.
Step 3 Remove the cover lock nut, guarding, and ferrule from the DPJ end connector
using the feeder window wrench shipped with pre-fab. modules.
Step 4 Place the cover lock nut and guarding along a cable into the plastic-coated metal
hose, as shown in
Issue 07 (2022-12-15)
Use a small cutter or a pair of scissors to cut the hose at the joint between
the plastic-coated metal hose and the end connector at an angle of 30 to 45
degrees, as shown in
Figure A-6 Cutting a hose
Trim any burrs on the cut.
Figure
A-7.
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Ferrule
(4) Cover lock nut
N/A
Figure
A-6.
A Basic Installation Operations
114

Advertisement

Table of Contents
loading

Table of Contents