FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
● Labels must be securely attached.
● Labels must be attached in eye-catching positions on cables for ease of
maintenance.
● The labels on both ends of a cable must be the same.
----End
A.2 Preparing Cable Terminals
Preparations
Tools: hydraulic pliers, heat gun, and crimping tool
Materials: heat shrink tubing, DT terminal, OT terminal, and cord end terminal
Documents: none
Skill requirement: common technician
Procedure
Step 1
Figure A-15
Figure A-15 Preparing a DT terminal
(1) Cable
(4) Hydraulic pliers
Step 2
Figure A-16
Issue 07 (2022-12-15)
NO TICE
shows how to prepare a DT terminal.
shows how to prepare an OT terminal.
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Heat shrink tubing
(5) Heat gun
A Basic Installation Operations
(3) DT terminal