Optional) Installing The Electric Heating Belt - Huawei FusionModule1000A40 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
Step 4 Place batteries in the battery cabinet from bottom to top and from left to right.
Step 5 Connect power cables between batteries and reinstall the insulation covers.
Figure 9-3 Place the batteries
(1) Battery
----End
Follow-up Procedure
Verify the battery connections. Ensure that the battery quantity and cable
connections comply with the design and the cables are reliably installed.

9.2 (Optional) Installing the Electric Heating Belt

Prerequisites
The pre-fab. modules have been installed.
Preparations
Tools: None
Materials: low-temperature component suite
Skill requirements: cooling engineer, common technician
Issue 07 (2022-12-15)
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Installing Devices Inside Pre-fab. Modules
78