A.1.6.2 Installing Waterproof Metal Connectors
Prerequisites
Preparations
Tool: wrench dedicated for the feeder window
Materials: transparent sealant, sealing rubber strip
Documents: none
Skill requirement: skilled technician
Procedure
Step 1 Disassemble a waterproof metal connector using the dedicated feeder window
wrench shipped with the pre-fab. module, and take the plug out of the connector,
as shown in
Figure A-10 Disassembling a waterproof metal connector
Step 2 Route a cable into the pre-fab. module through the waterproof metal connector,
as shown in
● People inside and outside the pre-fab. module should work together to route
the armored power cable to the specified connection position inside the pre-
fab. module.
● To facilitate operation during internal routing, you can remove some top plate
in the pre-fab. module aisle.
Issue 07 (2022-12-15)
Do not operate a feeder window outdoors under bad weather conditions if no
shelter is available.
Cables have been mounted on cable trays.
Cables need to be routed into a feeder window using waterproof metal
connectors.
Figure
A-10.
Figure
A-11.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
A Basic Installation Operations
116

Advertisement

Table of Contents
loading

Table of Contents