3.2.1 (Optional) Concrete Platform Scenario

3.2.2 (Optional) Base Installation Scenario

Issue 07 (2022-12-15)
Build concrete platforms on the selected installation site.
Figure 3-1 Concrete platform (unit: mm)
(1) Concrete platform
NO TICE
The minimum cross-sectional area of a concrete platform must be 2900 mm x
1000 mm. The concrete platforms must be 500 mm higher than the ground to
ensure efficient drainage.
Load-bearing capacity of concrete platforms: meets the requirements of the
maximum weight of a pre-fab. module 25,000 kg and NEBS Zone 3
antiseismic requirements.
NO TE
Recommended load-bearing capacity calculation: Maximum weight of a pre-fab.
module 25,000 kg x 3 (NEBS Zone 3 requires amplitude acceleration 3G) x 1.5 (0.5
times the engineering construction error and margin)/Effective support contact area
(The effective contact area in the concrete platform installation scenario is 4 x 272
2
cm
.)
The horizontal error between concrete platforms must be less than 5 mm.
Concrete pads or passages with the load-bearing capacity meeting local civil
work standards can be built on the site outside the concrete platforms for
access and servicing.
Build concrete platforms on the selected installation site.