Removing The Pre-Fab. Module Protective Cover - Huawei FusionModule1000A40 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
Step 2 On the basis of the reference points, mark the mounting positions for the four
corner fittings of a pre-fab. module using an ink fountain and long leather
measuring tape.
When marking the mounting positions for corner fittings, ensure that the four
lines form a rectangle.
Figure 5-1 Concrete platform (unit: mm)
(1) Concrete platform
----End

5.1.2 Removing the Pre-fab. Module Protective Cover

Prerequisites
The weather condition is good without rain or snow.
Context
A protective cover is installed to protect the pre-fab. module during transportation.
Preparations
Tools: safety helmet, safety belt, step ladder, protective gloves, utility knife
Materials: none
Skill requirement: common technician
Issue 07 (2022-12-15)
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Ground
5 Installing Pre-fab. Modules
(3) Angle steel
40

Advertisement

Table of Contents
loading

Table of Contents