Step 3 Remove the transparent cable protection panel from the power PDB busbar.
Step 4 Route the external input power cables into the power PDB through the cable holes
at the bottom, and route them out along the cable bridge above the cable holes.
N+X scenario: 1L1–1N connects to the mains; 2L1–2N connects to the genset.
2N scenario: 1L1–1N connects to mains 1; 2L1–2N connects to mains 2.
Figure 10-2 Connecting input power cables for the power PDB
Step 5 Connect the cables by following the instructions in
Techniques.
After connecting the cables, seal the two cable holes at the bottom of the power
PDB using waterproof sealing putty.
Step 6 Reinstall the transparent cable protection panel, and close the door of the power
PDB.
----End
Issue 07 (2022-12-15)
NO TICE
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
10 Installing Cables Outside Pre-fab. Modules
A.1 Cable Installation
99

Advertisement

Table of Contents
loading

Table of Contents