FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide
5.1 (Optional) Concrete Platform Scenario
5.1.1 Determining the Pre-fab. Module Installation Position
Prerequisites
●
●
Concrete platform levelness is critical to pre-fab. module installation. Ensure that
the concrete platform meet requirements before installing pre-fab. modules.
Context
Before installing pre-fab. modules, determine their installation positions and
directions based on site space.
Preparations
Tools: marker, ink foundation, long leather measuring tape
Materials: none
Skill requirement: skilled technician
Procedure
Step 1 Determine the reference points for installing pre-fab. modules on the concrete
platforms. Mark the reference points using a marker.
Issue 07 (2022-12-15)
5
Installing Pre-fab. Modules
The field meets site requirements.
Before installing pre-fab. modules, check the height of concrete platforms and
ensure that the height (altitude) error between the upper surfaces of all
platforms does not exceed 5 mm.
CA UTION
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Installing Pre-fab. Modules
39