6.2 (Optional) Installing a Rain and Snow Cover
Preparations
Tools: socket wrench, Phillips screwdriver, glue gun, step ladder
Materials: rain and snow cover, mounting plate of the rain and snow cover, rubber
pad, white sealant, rain and snow cover bolt, washer
Skill requirement: common technician
Procedure
Step 1 Secure the mounting plate of the rain and snow cover at the top of the pre-fab.
module door.
There are two rows of screw holes on the top of the pre-fab. module door. The
screws on the mounting plate of the rain and snow cover need to be installed in
the three holes in the lower row, as shown in the following figure.