2.3 Pre-fab. Module Entry Requirements

The following describes the requirements for working in the FusionModule1000.
Item
Before entry
Entry
preparations
Working in the
data center
After all work is
finished
Check before
leaving
Follow-up
Procedure
Replace, maintain, and troubleshoot components of the FusionModule1000 only in
the presence of qualified engineers.
Issue 04 (2021-02-10)
Requirement
● Obtain the entry permit.
● The detailed operations are performed based on the requirements
specified by the manager of the FusionModule1000.
● Obtain ESD clothes and shoes.
● Remove dust from tools and materials that need to be taken into the data
center, and make a record.
● Do not bring in forbidden items, such as storage devices, cameras, or
portable hard disks into the FusionModule1000.
● Only professional personnel are allowed to work in the data center and
only in the presence of designated personnel.
● Obtain permission from designated personnel and take necessary
precautions and preventive measures before entering the
FusionModule1000 and performing any operation which may affect the
normal running of the FusionModule1000.
● Do not perform any unauthorized operations.
● Pack up the tools and surplus materials.
● Clean up and organize the equipment room environment according to
environment requirements.
● Accept the operations and make records about any operations performed.
● Check the items to be taken out.
● Sign out.
● Return the ESD clothes and shoes.
● If any faulty component is replaced, dispose of the removed faulty
component.
NO TICE