FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
When marking the mounting positions for corner fittings, ensure that the four lines form a
rectangle.
Figure 4-1 Concrete platform (unit: mm)
(1) Concrete platform
----End
4.1.2 Removing the Pre-fab. Module Protective Cover
Prerequisites
The weather condition is good without rain or snow.
Context
A protective cover is installed to protect the pre-fab. module during transportation.
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
4 Installing Pre-fab. Modules
(2) Ground
(3) Angle steel
13