3.2.5.7

Parameter window A: Metering (Wh)

In parameter window A: Metering (Wh), the settings for the main meter and the intermediate meter or out-
put A are undertaken.
Send "Meter reading"
Send "Intermediate meter reading"
Options:
The meter readings Meter and Intermediate meter are sent according to the parameterization options se-
lected. Setting of the cycle time and enabling of the request object occurs in the parameter window
ing
(Wh), page 33.
Furthermore, the readings of the Intermediate meter are sent on the bus at start and/or stop.
Trigger 1 (Start) is activated by
Options:
1 bit object: The 1 bit communication object Receive trigger 1 (A: Intermediate meter) is enabled. The
intermediate meter starts if a telegram with the value 1 is received on this communication object.
Time: The 3 byte communication object Trigger 1 change time (A: Intermediate meter) is enabled.
The start time can be modified using this communication object. The following parameters appear:
no, update only
cyclically
on request
cyclically and on request
1 bit object
Time
SE/S 3.16.1 | 2CDC 505 084 D0203 73