Optional) Base Installation Scenario - Huawei FusionModule1000A20 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
(1) Concrete platform

2.2.2 (Optional) Base Installation Scenario

Issue 02 (2020-01-15)
Figure 2-1 Concrete platform (unit: mm)
The cross-sectional area of a concrete platform must be 700 mm x 700 mm. The horizontal
error between concrete platforms must be less than 5 mm.A concrete platform must be at
least 500 mm higher than the ground.
Determine the actual height of the concrete platforms based on the local drainage and weather
conditions.
The concrete platform should have a maximum load bearing capacity of 15,000 kg and the
recommended seismic acceleration is 3 g. The specific strength is calculated based on the
contact area (a single supporting point installed on the ground is 400 cm
Concrete pads or passages with the load-bearing capacity meeting local civil work
standards can be built on the site outside the concrete platforms for access and servicing.
Build concrete platforms on the selected installation site.
Copyright © Huawei Technologies Co., Ltd.
(2) Ground
(3) Angle steel